Telson Resources Inc. Restarts Operations for Production at Campo Morado

https://www.telsonresources.com/images/NewsReleases/2017_News_Releases/TSN_NR_170_Oct23_2017.pdf

Vancouver, British Columbia, October 23, 2017
Highlights:
 Starting at a mining and processing rate of 1,400 tonnes per day
 Production expected to increase to 2,500 tonnes per day during the next 6 to 12 months
 First concentrate shipments expected to be sent to Trafigura first week November 2017
Telson Resources Inc. (“Telson” or the “Company”) (TSX Venture – TSN.V) is pleased to inform shareholders that ore processing at an initial mill throughput start up rate of approximately 1,400 tonnes per day has been initiated at the Company’s 100% owned Campo Morado Mine.
The first two years of production are planned to be mined from the G9 and El Largo ore bodies in areas of elevated gold and silver values within polymetallic base metal zones having average grades of 1.8 g gold/t, 142.7 g silver/t, 3.99% zinc, 0.62% copper and 1.07% lead.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s