CABORCA, Mexico, Jan. 21, 2020 (GLOBE NEWSWIRE) — Mexus Gold US (OTCQB: MXSG) (“Mexus” or the “Company) announced its plan for the coming year and gave an update on its various projects and holdings located throughout Mexico. On January 7th the company began mining on the Julio vein/shear zone via a 300 x 20 meter open pit at its Santa Elena mine. This area had been blasted during the first week of January. Approximately 4500 tons of mineralized material has been mined to date with 3000 tons having been run through the crushing circuit. The resulting ¾” minus material was placed on the heap leach pad with leaching resuming on January 13th. Assays of the head material have shown 4 g/t Au and 9 g/t Ag with some areas testing as high as 16 g/t Au. The Julio material was added to 12,000 tons of Lucky Strike mineralized material which averages 1.2 g/t Au. Solution from the heap leach started returning to the pregnant pond January 15th showing a grade of .35 g/t Au of pregnant solution. The flow and returns have continued to increase with recent readings showing .45 g/t Au per ton of solution. On January 17th the company started processing the pregnant solution at a rate of 1 ton of solution per 2 minutes through the Merrill Crowe and activated carbon gold recovery systems. The use of both systems will ensure maximum recovery. Since January 17th the company has recovered 15 oz. of gold. Recovery will increase as the size of the heap pad grows allowing for additional solution to be run through the system.